Hello Experts! We use QE71 for RR and UD for calibration. In the dynamic selection when I choose the option to filter it through equipment number, it outputs all the inspection lots which has different equipment number associated in the order. Ca...
Hello Experts, We created a K (cost center) PO and the material has QM active. After GR, an inspection lot was created. We cancelled the material document, but it didn't cancel the lot. It is still in REL, CAL status. I tried canceling the lot t...
Hello Experts! We have an MTO scenario. Sales order comes in which drives the demand to component level. Sales -> MRP-> Planned Order-> Process Order. When the process order is created, under the goods receipt tab, the goods receipt...
Hello Experts! We have a requirement to display the SLED in MM/DD/YYYY format. We need to use the period indicator M in the plant data storage view of the material master. When we use this is indicator, the SLED date changes to MM/YYYY form...
Hello Experts, MRP runs in the background with MDBT variant with parameters 1 3 1 1 1. For the components, there is scheduling agreement and source list with correct validity dates. After the background job it creates Purchase requisitions even t...