on 04-01-2020 2:05 PM
Hi Team,
can you please suggest why system is producing allocation structure error as below while creating settlement rule for network activity we are using network Profile (activity acct. assignm)settlement.jpg
& if we assigned strategy 20 to project profile then new error came as following.,,,,,,,,,,,,,
Message no. ORB503
The parameters controlling settlement rule generation are defined in the settings for the strategy. The applicable settings are determined using the master data characteristics.
The following master data characteristics were determined for the current object:
The system could not determine any settings for strategy 20 for this combination of characteristics.
Object not processed.
Add the appropriate entry to the settings for strategy 20.
Regards,
Sanjeev
Hi Paulo,
however i have fixed earlier issue but now new error came as below.
here i have change allocation structure as well before running settlement but issue yet to not resolve can you suggest some thing on?
Message no. KD503
During settlement, the system puts the sender debits into groups (assignments), which are settled using the same settlement cost element. The settlement assignment is made in the allocation structure, which is stored in the settlement rule for the sender (under settlement parameters).
Cost element 5509000 cannot be assigned to a settlement cost assignment in allocation structure A1, and therefore it cannot be assigned to a settlement cost element.
Possible solutions are as follows:
Regards,
Sanjeev
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sanjeev,
Maybe try to check the allocation structure that sits on your settlement profiles. Maybe it does not exist exactly as the message is saying.
Regards,
Paulo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Paulo,
thanks for your quick response.
i went through your blog and found same setting we have in our system but still that error is coming.
let me explain a bit what happen we performed CJB2 which got fail then i decided to add settlement rule manually which we did and its work for Wbs but for network it won't work while i have made receiver category wbs and put same wbs where activity is sitting. then back during back it say "Enter an existing allocation structure" hence unable to back from settlement rule screen.allocation-structure.jpg
Regards,
Sanjeev
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sanjeev,
Please validate what customizing you are missing:
https://blogs.sap.com/2014/12/23/generate-settlement-rules-for-network-activities/
Regards,
Paulo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.