on 11-21-2023 12:15 PM
Dear,
We are currently trying to implement scope item 4B5 - Predictive MRP. Whenever we try to schedule the pMRP simulation (app Schedule pMRP Simulation Creation), we get the following error:
However, when performing the consistency check in Manage Production Versions (C223), the check returns no errors.
Also in Process Production Versions, the check is successful for this production version. We do not know how to fix this, as we do not see any inconsistencies when checking manually neither.
Hope you can help.
Kind regards
Hi Emma, try to create planned/production order with production version manually.
SAP should raise specific error.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Can you please provide the solution?
Thanks & BR
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.