on 06-13-2023 11:56 AM
Hello Expert,
Below is the requirement to map the rebates through condition contract:
The customer receives free products upon achieving one specific target. The FOC products could be different from the funding products (the products that the customer has to buy to qualify for the rebate).
In this case how we can determine the accruals from the funding products to the FOC products.
Please suggest how we can map this process through condition contract in S/4.
Thanks and Regards,
Pankaj
Hello Pankaj,
this has already been done as a project solution. Basically, you have to connect the condition contract with a value/quantity contract. Definitely no need for an extension.
Regards,
Thorsten
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
9 | |
8 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.