on 11-29-2008 5:45 AM
HI SAP Gurus,
I am getting a error while creating PIR's in MD61.
The input is Req. plan Number, Plant, Version, Planning Horizon: From-01.12.2008 to 02.01.2010
SAP system is not allowing to create or copy PIRu2019s for December-2008. Following is the message:-
u201C02.01.2011 date comes after end of valid factory calendar(Please correct)u201D.
what must be the problem?
Please Help.
Thanks & Regards,
Santosh
Hi,
Check Valid to date of your Factory Calendar.T.code is SCAL.
Regards,
Dhaval
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Dhaval Choksi,
My Planning Horizon is from 01.12.2008 to 02.01.2010. when we enter this the system is throwing a error saying that u201C02.01.2011 date comes after end of valid factory calendar(Please correct)u201D.
but when i change the Planning Horizon as from 01.12.2008 to 04.01.2008, then there is no error.
why this is happening?
Thanks & Regards,
Santosh
User | Count |
---|---|