Problem in Creating PIR in MD61

santosh_kanta3
Participant
0 Kudos

HI SAP Gurus,

I am getting a error while creating PIR's in MD61.

The input is Req. plan Number, Plant, Version, Planning Horizon: From-01.12.2008 to 02.01.2010

SAP system is not allowing to create or copy PIRu2019s for December-2008. Following is the message:-

u201C02.01.2011 date comes after end of valid factory calendar(Please correct)u201D.

what must be the problem?

Please Help.

Thanks & Regards,

Santosh

View Entire Topic
dhaval_choksi3
Active Contributor
0 Kudos

Hi,

Check Valid to date of your Factory Calendar.T.code is SCAL.

Regards,

Dhaval

santosh_kanta3
Participant
0 Kudos

Hi Dhaval,

Thanks for ur reply. I checked my Factory Calender, it is 2010. but my input is 01.12.2008 to 02.01.2010. then why the system is throwing that error?

please reply.

Thanks & Regards,

Santosh

dhaval_choksi3
Active Contributor
0 Kudos

Hi Santosh,

Check Planing Horizon in Initial screen of MD61.

Regards,

Dhaval

santosh_kanta3
Participant
0 Kudos

Hi Dhaval Choksi,

My Planning Horizon is from 01.12.2008 to 02.01.2010. when we enter this the system is throwing a error saying that u201C02.01.2011 date comes after end of valid factory calendar(Please correct)u201D.

but when i change the Planning Horizon as from 01.12.2008 to 04.01.2008, then there is no error.

why this is happening?

Thanks & Regards,

Santosh

pravin_kusumbe2
Participant
0 Kudos

Please check the planning table in MD25

santosh_kanta3
Participant
0 Kudos

Hi Pravin.

thankd for ur reply. there is no planning calendar maintained.

Thanks & Regards,

Santosh Kanta

santosh_kanta3
Participant
0 Kudos

Hi

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Extende the holiday calender before extending the factory calender then cheack.

Regards,

R.Brahmankar