HI SAP Gurus,

I am getting a error while creating PIR's in MD61.

The input is Req. plan Number, Plant, Version, Planning Horizon: From-01.12.2008 to 02.01.2010

SAP system is not allowing to create or copy PIRu2019s for December-2008. Following is the message:-

u201C02.01.2011 date comes after end of valid factory calendar(Please correct)u201D.

what must be the problem?

Please Help.

Thanks & Regards,

Santosh

View Entire Topic
Former Member
0 Kudos

Hello Santosh

it cause your replenishiment date is out of your factory calendar.

there has same resolution, but the best solution is maitian your factory calendar to 2020 or more.

Kim

santosh_kanta3
Participant
0 Kudos

Hi kim,

But when i change my Planning Horizon in the 'To' to just 2 days, then the system is not showing any error. or even when i change the Planning period from 'W' to 'D'. there is no error. in fact the error is only for 'W' not for others.

what must be the problem.

Thanks & Regards,

Santosh

Former Member
0 Kudos

Hello Santosh

the caculate logic is

Current date + Planning horizon(work day) + rescheduling date(work day) + 1 Week(if you set lot-size is "WB" in Material master)

currently the result is out of the during factory calendar.

yes you can maintain the planing horizon to more small or change the lot-size from "W" to "D"

it can resolve temporarily, but with the passage of time will occurs again.

so i think the best resolution is maintain the factory calendar to more big.

thanks