on 11-29-2008 5:45 AM
HI SAP Gurus,
I am getting a error while creating PIR's in MD61.
The input is Req. plan Number, Plant, Version, Planning Horizon: From-01.12.2008 to 02.01.2010
SAP system is not allowing to create or copy PIRu2019s for December-2008. Following is the message:-
u201C02.01.2011 date comes after end of valid factory calendar(Please correct)u201D.
what must be the problem?
Please Help.
Thanks & Regards,
Santosh
Hello Santosh
it cause your replenishiment date is out of your factory calendar.
there has same resolution, but the best solution is maitian your factory calendar to 2020 or more.
Kim
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Santosh
the caculate logic is
Current date + Planning horizon(work day) + rescheduling date(work day) + 1 Week(if you set lot-size is "WB" in Material master)
currently the result is out of the during factory calendar.
yes you can maintain the planing horizon to more small or change the lot-size from "W" to "D"
it can resolve temporarily, but with the passage of time will occurs again.
so i think the best resolution is maintain the factory calendar to more big.
thanks
kim
User | Count |
---|---|
82 | |
8 | |
7 | |
6 | |
6 | |
3 | |
3 | |
3 | |
2 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.