Requirement: Update Production Order Header Status (or) Operation Staus by Function Module FM: I_CHANGE_STATUS
Action 1:
Get the current Status of the Production Order: 1001230 first, using Function Module STATUS_READ (INPUT: OBJNR: OR000001001230...
Hi All,When creating the Control Cycle in KANBAN, System is picking the Control Cycle Number from in the Internal Number ranges only, but not the Manually entered value. even though the External Nuber ranges were maintained & check for the External N...
Batch Derivation Concept in Process Manufacturing
This Batch Derivation Process that enables you to do the following for Batch Master data and Classification data to be derived from the Component Batches to the Produced batches:
Transfer
Display for ...
This is the Most commonly faced/reported issue during MRP run
Issue Reported
During the MRP run, System not creating any Procurement proposals and getting the message “No procurement proposals changed” even though there is a clear requirement.
More d...
Business Scenario:
During the Confirmation of the Process Order, which is activated with Backflush (Auto GI, during the confirmation), System is not allowing the Additional Good issues/increase the Component Quantity manually. Getting the Error messa...
Hi Susumususu SanGreetings of the Day.It's Great Article.Thanks A Lot for sharing this Detailed & Most useful info at one place with series of Blogs together. Keep sharing such Wonderful Articles.Thanks & RegardsRaja
Hi AnthonyTECO & DLV are the two independent statuses of an Order.Meaning, without DLV also, there is possibility, Order can get TECO status, at the same time, once the Order has DLV, doesn't mean it is updated with TECO Status. (Attached the screen ...
Hi Pradeep,Without specifying the Batch Number (or) the Values, from where system can pick up the Value for the Receiver? In the Standard Derivation Strategy, you will link the Sender(s) with Receiver.Without specifying the Sender, it looks bit of am...
Hi Yes, it is possible, to Derive the Value from the Multiple Inputs, & Select the Highest(or)Lowest value of the input Batches as per the Business requirement (Attached an Example of one such case, where there 3 Sender Materials, with different Inpu...