Hi Experts ,
How do I get the Latest finish dates in the BAPI CNECP_MAINTAIN for Planning Form .
I Can find it in Cost Lines ,but when I use a Planning Form/Cost Model I cannot see any inputs for Latest Finish Dates
Note: Planning is done at WB...
Hi Experts,
I have created Cost Plan using ECP with Planning Form manually.
Now when I try to test the same using BAPI CNECP_MAINTAIN for my upload prog. I am getting the error
CKECP 117 The Specified Planning Form was not found.
I have crea...
Hi,
I have a scenario where Sales order line item is created for Deferred Revenue and account assigned to WBS . Since actual revenue is not recognized in the start but later.
I have a query, how would the system behave with Planned revenue.
Wo...
Hi Experts,
I have a scenario for SD Quarterly billing.
In S_ALR_87013543 report system calculates planned revenue as Condition value multiply by total billing quarters.
If my condition amount is 100 for 3 nos ,them condition values = 100x3 =3...
Hi Experts,
I have created a billing WBS and account assigned it to Sales order line item.
The item category is for one time payment i.e. no billing plan.
All Config settings in place
In S_ALR_87013531 report ,I cannot see any planned revenue...
Hi All ,Error was resolved ,The issue was resolved by maintaining DEL_OLD_ITEMs and DEL_OLD_MODEL_VALUE to 'X'And also used the BAPI in test sequence CNECP_MAINTAIN and BAPI_TRANSACTION_COMMITThanks.Kehkashan A J
Hi all,Thanks for your help.The issue was resolved by implementing the note:828853The system was taking condition type and billing dates into consideration for calculating planned revenue values .This works fine for monthly billing.When quarterly bil...
Hi ,Please find the below screen shots.for qty =2 no's ,value =12,000/-quarterly billing for one year ,gives 4 quarters.approx 1,43,225/- is correctly being calculated But in PS report it calculates 2 X 6000/- = 12000/-12000 X 4 quarters = 48,000/-W...
Hi Ken,In this scenario for Sales Order ,advance billing is used .The customer is billed in advance and this Revenue is considered as deferred revenue.Subsequently the deferred revenue will be converted to actual revenue later.Thanks,Kehkashan