Hello Experts,
we are managing SD sched agreement. The material has an alternative UoM, base is KG, alternative is M(eter). For the material, the 'product unit'management is active, that is, every batch has its own conversion factor.
The SchedAgr...
Hello all,
i would like to upload to the system PIR for the header material of a sales kit, to trigger production for the procurement of the material in its bill of material in a MTS prospective, before the real sales order is available. These comp...
dear experts,
we implemented a process for purchasing of components in maintenance order. Purchase requisition is triggered at maintenance order release. The Flexible workflow is activated at item level for PR, and it works for all the component ma...
Hello experts,
i found that planned orders 'PP firmed', with fixed date and quantity, are rescheduled by the system. As far as i know, this should be not possible at all. We suspect that is related to CTP check, because the material are finished pa...
Hello all,
i have an issue in V_V2 run. If i run it using a specific material number in the selection screen, the new atp date is correct. If i run it without material number, so checking all the sale order portfolio, the atp dat for the same order...
hello kumar,hello for the answser.i've already investigated in these strategies but none fulfill my requirement. first of all the kit header material is never managed in stock, so strategies 50 ATO does not work. I prefer not to use strategy 70 on th...
Hello all,i'm not able to solve this problem. Planned orders with fixed date flag, and so PP-firmed, are rescheduled by standard heuristic SAP_PP_002, but not everytime the MRP runs. Is this a standard behaviuor? In which situations operation with 'f...
no pp/ds horizon is set. In fact, the orders is confirmed succesfully after a certain date, not in the short period.I've already read the note you suggest, but bucket-oriented capacity check is not usefull in my senario. We use the time-continuous ch...