Hi All,
We are using MTO scenario and version S/4 HANA 1809. After MRP run, Planned Orders are created for Sales Order. When i check in the Planned Order under Assignment tab, Sales Order is visible, but Customer name is blank. Could you please let...
Hi All,
I have issue with Round Value. My planning strategy is 40. Using procurement type E. My lot size is MB. I have maintained Min Lot size 5,700 and Max Lot Size 39,600. I have kept Rounding Value as 1,000. PIR requirements is 4,000 per mont...
Hi All,
We are working SAP S/4 HANA. We are using Planning Strategy 40 with Consumption mode -2, Backward Consumption-30 and Forward Consumption-40.
Have uploaded PIR's on 1st March 2018 for 18000. I do have SO's in March and in Jan & Feb 2018. ...
HI SAP Gurus,I am getting a error while creating PIR's in MD61. The input is Req. plan Number, Plant, Version, Planning Horizon: From-01.12.2008 to 02.01.2010SAP system is not allowing to create or copy PIRu2019s for December-2008. Following is the ...
Hi SAP Gurus,I am facing one problem. the scenario is as follows.client is having 4 plants. i am doing Production Order for Semi finish material in Plant 2. but Raw material stock material is in Plant 4. i suggested to transfer stock fom plant 4 to p...
Hi Brahmankar,Yes Planned Order is not supporting it. I would like to know if Planned Order doesn't support, then why there is a Customer field in Assignment tab of Planned Order.Thanks & Regards,Santosh
Hi Brahmankar,Thanks for your reply and sorry for replying you late.We are in MTO scenario. When i convert planned order to Production order, yes all the details like Sales Order number, BP number and its name will be there.Thanks & Regards,Santosh
Hi kim,But when i change my Planning Horizon in the 'To' to just 2 days, then the system is not showing any error. or even when i change the Planning period from 'W' to 'D'. there is no error. in fact the error is only for 'W' not for others.what mu...
Hi Parag,In routing, select the operation, to which u want to assign PRT. then click on PRT tab or press F8. You will get a pop - up window for PRT. there are four typrs of PRT's. select which PRT you want to assign. ex. material, document, equipment...